In short
Force majeure is an event beyond a party's control that prevents it from performing the contract. Under US and English law, it exists mostly through the contract's force majeure clause, which lists the events and their effects: the obligation is suspended or, if the event lasts, the contract can be ended, with no damages owed.
What is force majeure?
Force majeure excuses a party that could not perform because of an event it did not control. In civil-law countries, the code defines it. In the United States and under English law, the contract's clause defines it: the events covered, the conditions, the notice, the effects. In a supplier contract, the party that invokes it is most often the supplier.
Without a clause, what the law offers is narrower. For sales of goods in the United States, a delay or a failure to deliver is not a breach when performance has been made impracticable by an event whose non-occurrence was a basic assumption of the contract, and the seller has to notify the buyer (UCC § 2-615).
Faced with a breach of contract, it is the first defense to check: if it fails, you keep all your remedies.
The conditions
A well-drafted clause sets cumulative conditions. The event has to be:
- beyond the party's control: arson on its premises can be, a mistake by its teams is not;
- unforeseeable at signature: an epidemic already declared or a strike already announced was foreseeable;
- impossible to overcome: if a backup site or another subcontractor allowed performance, even at a higher price, the condition is not met;
- the direct cause of the failure complained of.
Everything turns on the text: courts tend to read these clauses closely, and an event the clause does not cover is not force majeure just because it is serious.
Supplier examples: what holds up and what does not
A court decides case by case, contract in hand; these guideposts only show tendencies.
| Event invoked | Can be accepted if… | Usually refused if… |
|---|---|---|
| Fire, flood | No reasonable measure could have avoided its effects | The backup site required by the contract did not take over |
| Strike | An outside strike (transportation, ports), unexpected and impossible to work around | An internal dispute the supplier could settle |
| Failure of a subcontractor or a hosting provider | The event that hits it meets the conditions itself, and nobody could replace it | The supplier could have switched partners |
| Cyberattack | An exceptional attack despite the required security measures | Patches not applied, backups missing or never tested |
| Rising costs | Rarely, and never alone | Performance remains possible, at a higher price |
| Decision of the authorities (closure, sanctions) | It prohibits performance and was not foreseeable at signature | It was announced, or only makes performance more expensive |
How to invoke or contest force majeure
By notifying the other party in writing, with evidence. The other party can accept it or contest it; if they disagree, a court decides.
Notice
A well-drafted clause requires a written notice within a short time: what event, since when, which obligations it prevents, for how long, with what measures to limit its effects. On receipt, answer in writing: you take note without accepting that it is force majeure, you ask for the supporting documents and a dated recovery plan, and you point out that the other obligations continue.
Deadlines
If the clause makes the notice deadline a condition, a supplier that gives notice three weeks after the event risks a refusal. Even a temporary event can justify ending the contract when the delay defeats its purpose: training planned before a March 15 launch is useless in April (fictional example). The clause also sets the duration beyond which either party can terminate: thirty days in the sample below. If a supplier stays silent about a delay, put it in writing, for instance with our notice to cure letter.
Evidence
The burden of proof is on the party that invokes force majeure. Ask for dated documents: decision of the authorities, incident report, insurance claim, exchanges with the subcontractor, records of the continuity plan. Check that the event really connects to the obligation at issue: a fire in Chicago does not explain a delay on services delivered from Dallas (fictional example).
Payment and suspension
During the suspension, the supplier owes neither damages nor, as a rule, liquidated damages; if the service level agreement excludes force majeure, the period is also left out of the availability calculation. For the price, write that services not provided are not invoiced: a subscription of $12,000 a month, interrupted 10 days out of 30, is then invoiced at $8,000 that month (fictional example).
If the event hits you, your payments usually remain due: many clauses exclude payment obligations from force majeure. And if your sites close and you can no longer use the service, a clause written for the supplier gives you nothing: provide for that case in the clause.
If the event is permanent, the contract ends. Write that a fee paid in advance for a period not served is refunded.
Drafting the clause
Be wary of clauses that set out a long list of events “deemed” to be force majeure, down to outages at the supplier's own providers: depending on their wording, they relieve it of proving the conditions. For the buyer, a useful force majeure clause includes:
- a definition with its conditions and written exclusions;
- a written notice within a short time, with set contents;
- the duty to limit the effects, what happens to the price, the use of a third party;
- a duration beyond which either party can terminate;
- what happens to your obligations if your own sites close.
Section [X]. Force majeure [X].1. A force majeure event is an event beyond the reasonable control of the affected Party, that could not reasonably have been foreseen when the Agreement was signed, whose effects cannot be avoided by appropriate measures and that prevents that Party from performing an obligation. The following are not, in themselves, force majeure events: [a strike of the Provider's personnel; the failure of one of its subcontractors; a cyberattack whose effects the security measures of Schedule [n] would have avoided; an increase in the Provider's costs]. [X].2. The affected Party shall notify the other in writing within [five (5)] business days, stating the event, the obligations affected, the expected duration and the measures taken, with supporting documents. The affected obligations are suspended from the date of the notice. [X].3. During the suspension, the Provider shall implement its business continuity plan. Services not performed are not invoiced, and the Customer may entrust them to a third party. [X].4. If the event lasts more than [thirty (30)] days, either Party may terminate the Agreement by written notice, with no compensation. [X].5. If an event beyond the Customer's control, such as the closure of its sites by the authorities, prevents it from receiving the services, it may suspend their performance and payment; Section [X].4 applies.
The positions most favorable to the customer (suspension from the date of the notice, use of a third party, paragraph 5) have to be negotiated; have the clause reviewed by your counsel. It is among the essential clauses of a supplier contract.
When an event hits several suppliers, a Naigo tabular review puts the same question to a whole batch of contracts, with a ready-made “Force majeure” column; each answer cites its page and the exact passage (see supplier contract management).
GuideSupplier contract clauses: the key terms to check before signingThe clauses to check in a supplier contract: scope, price, term, liability, service credits, force majeure, confidentiality, termination. With a checklist.Read the definitionForce majeure or hardship
Force majeure assumes that performance is prevented. Hardship covers performance that has become excessively costly after an unforeseeable change of circumstances.
| Force majeure | Hardship | |
|---|---|---|
| During the crisis | The obligation that is prevented is suspended | The affected party keeps performing during the renegotiation |
| Outcome | Resumption, or the end of the contract if the event lasts | An agreement, or the exit the clause provides for |
| Fictional example | The supplier's only data center is destroyed | The energy cost of that data center triples |
A supplier that invokes force majeure for a rise in its costs has picked the wrong clause.
Frequently asked questions
Is a pandemic a force majeure event?
Not automatically. It depends on the wording of the clause, and on whether the epidemic or the measures taken against it prevented performance, and did not merely complicate it or make it more expensive. A contract signed when the epidemic was already known is a poor fit: it was no longer unforeseeable.
Do you have to pay during force majeure?
For your own payment obligations, usually yes: many clauses exclude them from force majeure. For the services the supplier does not provide during the suspension, no if the contract says they are not invoiced, which is why that sentence belongs in the clause.
Is war a force majeure event?
Not in itself. A war already under way at signature was, in general, foreseeable. One that starts afterward can be if it prevents performance: a site destroyed, a delivery prohibited by sanctions. The price increases it causes make performance more costly, not impossible: that is hardship territory.
Sources
Published on November 25, 2026
General information, current as of the date shown: it does not replace advice from a legal professional on your situation.