RFQ (request for quotation): definition and use

In short

An RFQ (request for quotation) asks several suppliers for a price on a need that is already precisely defined: quantities, specifications, lead times. It is used when the solution is known and only the price decides, with equal compliance. The quotes received are then compared line by line, on the same pricing sheet.

What does RFQ stand for?

RFQ stands for request for quotation, sometimes request for quote. The buyer knows exactly what to buy and asks several suppliers how much they would charge, within what time and on what terms. In construction and professional services, the same abbreviation can mean request for qualifications, where no price is asked yet; this page deals with the request for quotation.

The difference from an ordinary quote lies in the competition: the RFQ goes at the same time to several suppliers, with the same response format, so that the prices received can be compared. The difference from an RFP lies in the freedom left to the supplier. In an RFP, the supplier proposes its solution; in an RFQ, the solution is specified and the supplier only prices it.

When to choose an RFQ

The RFQ fits when three conditions are met:

  • The need is fully specified: model, drawing, quantity, service level, place and date of delivery.
  • Several suppliers can deliver exactly the same thing.
  • Nothing other than the price, the lead time and a few commercial terms should separate the quotes.

Typical examples: IT hardware on a manufacturer's model number, parts made to a drawing, supplies from a list, licenses for software already chosen, a standard service whose content is set (freight, cleaning to a specification). The RFQ is also useful at the end of an RFP, to decide between two suppliers on a scope that has become fixed.

Conversely, if the supplier can answer “we would do it this way instead,” you are in an RFP. An RFQ sent on a vague need produces prices that do not cover the same thing, and the cheapest will often be the one that understood the least.

What an RFQ contains

An RFQ is short, but nothing should be missing. Each omission becomes a supplier's assumption, and each supplier makes its own.

  • The precise description of each item or service: model, specification, drawing or applicable standard.
  • The quantities, and their split if deliveries are staggered.
  • The place, date and terms of delivery.
  • The required response format: a pricing sheet to fill in, with the same lines and the same units for all.
  • The items to price separately: shipping, installation, training, extended warranty.
  • The payment terms expected and the validity period requested for the quote.
  • The response deadline and the contact for questions.

An example, with fictional data: “Quote for 40 laptops, model [model], configuration [processor, memory, storage], delivered to Austin by [date] at the latest, three-year on-site warranty. Unit price before tax, shipping separate, quote valid for 60 days. Response on the attached pricing sheet before [date].”

DefinitionPricing sheet: definition and how to build one for an RFPThe pricing sheet of an RFP or RFQ: what it is for, how to build it so proposals compare line by line, and why the buyer sets the quantities.Read the definition

Comparing the quotes

Comparing quotes looks simple: take the cheapest. That is true on one condition, that all of them cover the same thing, hence the two habits below: a common pricing sheet and the total cost. Also check the extras the price does not show: the delivery time promised, the validity period of the quote, minimum order quantities. An unbeatable quote that is valid for ten days, or deliverable in three months, is not always the best deal.

The pricing sheet

The pricing sheet, which any sourcing software can enforce, gives all suppliers the same breakdown: same lines, same units, same quantities. Prices are then compared line by line, and an unusual gap stands out. A very low price on one line can signal an error or a misunderstanding of the need; get it confirmed in writing rather than discover it at delivery. If a supplier sends back its own format, ask it to fill in the sheet: otherwise you will do the conversion, and inherit its assumptions.

The total cost

The unit price is not the price paid. Add everything that depends on the supplier: shipping, installation, consumables, maintenance, warranty, payment terms and, for a recurring purchase, the price adjustment rule. An example with fictional figures, for 40 units:

Supplier ASupplier B
Unit price$950$990
Total for the units (× 40)$38,000$39,600
Delivery and installation$2,400Included
Three-year on-site warranty$1,600Included
Total cost$42,000$39,600

The supplier that is cheapest per unit costs $2,400 more in total. That is why you compare total cost, not unit price. To place the RFQ against the two other requests, see RFI vs RFP vs RFQ.

Frequently asked questions

How many suppliers should you invite to an RFQ?

Three to five, as for an RFP: three at least for the competition to mean something. Check before sending that each one can deliver exactly the need described, or its quote cannot be compared with the others.

RFQ or RFP: how do you choose?

Ask yourself one question: does the supplier have something to propose, or only a price to give? If it can propose a different solution, method or service, it is an RFP. If the need is fully specified and all will deliver the same thing, an RFQ is enough.

What is an RFQ in procurement?

A request for quotation sent to several suppliers, on a precisely defined need, to compare their prices, lead times and terms in the same response format.

Does an RFQ commit the buyer?

No, asking for a quote does not oblige you to order. The supplier, on the other hand, usually commits to its price for the validity period stated in its quote.