In short
A hardship clause lets a party ask to renegotiate the contract when an unforeseeable change of circumstances makes its performance excessively costly, without making it impossible. Performance continues during the renegotiation; if it fails, the clause says what happens next. Without one, US and English law offer little relief for a rise in costs.
What is hardship?
Hardship is a fundamental disruption of the economics of a contract by circumstances nobody could foresee when it was signed. The word comes from international trade: the UNIDROIT Principles of International Commercial Contracts speak of hardship where events fundamentally alter the equilibrium of the contract (Article 6.2.2). In procurement, the typical situation is a supplier invoking it to raise its prices.
Some civil-law countries have written the rule into their code: in France, since 2016, the affected party can ask for a renegotiation and, if no agreement is reached, a court can revise the contract or end it. The United States and English law have no general rule of that kind: a cost increase alone rarely excuses performance. The issue is therefore handled by the clause, or not at all.
The conditions
A hardship clause usually sets three cumulative conditions:
- The change has to be unforeseeable when the contract was signed. Compare the date of signature with the date the increase began: a contract signed when prices were already soaring makes a weak argument.
- Performance has to become excessively costly. If the clause sets no threshold, the point is argued case by case. Require figures specific to the contract: the affected cost's share of the price, the size of the increase and the effect on the margin.
- The party must not have accepted the risk. A fixed price over several years, or a clause that puts that cost on the supplier, can show that it had accepted it.
Renegotiation, then the exit
The procedure has three stages, and none of them lets the supplier set its price unilaterally:
- It asks for a renegotiation. Require a written request that describes the event and puts a number on its effect on the contract.
- It keeps performing during the discussion, at the contract price. That is what stops the mechanism from being used to buy time.
- If the discussion fails, the clause decides: termination with notice, an expert, or a court.
Our guide to a supplier price increase covers how to answer the letter itself.
Excluding hardship or setting rules for it
Excluding any revision protects your price, but the supplier can then price that risk into its proposal. Setting rules gives a predictable outcome: for the buyer, a good clause sets a measurable threshold, puts the burden of proof on the party that asks, keeps performance at the contract price and ends with a clean exit. It complements the price escalation clause, which absorbs ordinary variations.
Section [X]. Change of circumstances [X].1. This Section alone governs the consequences of a change of circumstances that could not reasonably have been foreseen when the Agreement was signed; the Parties waive any other right to have the Agreement revised or ended on that ground. [X].2. If such a change increases a Party's cost of performing the Agreement by more than [15]%, apart from the variations covered by the price adjustment of Section [Y], that Party may request a renegotiation in writing, with supporting figures. [X].3. During the renegotiation, limited to [60] days, the Parties perform the Agreement on its terms. [X].4. Any agreement is recorded in an amendment. A price adjustment applies only to the part of the price affected, for a set period, and decreases if the circumstances reverse. [X].5. If no agreement is reached within that period, either Party may terminate the Agreement by written notice, with [three] months' notice during which the Agreement is performed on its terms, with no compensation; the exit provisions of Section [Z] apply.
Adapt this sample and have your counsel review it. It gives both parties the same procedure, and that reciprocity helps get the clause accepted. In Naigo's supplier contract management module, the AI extracts the clauses of each contract with their source (section, page, document), and the list of tracked clauses can be extended in the settings: hardship can be one of them.
Hardship or force majeure
Force majeure assumes that performance is prevented; hardship, that it remains possible but becomes excessively costly.
| Hardship | Force majeure | |
|---|---|---|
| Performance | Possible, but excessively costly | Prevented |
| During the crisis | The party keeps performing | The obligation is suspended if the event is temporary |
| Outcome | An agreement, or the exit the clause provides for | The end of the contract if the event lasts |
A cost increase, even a sudden one, is therefore rarely force majeure: delivering costs more but remains possible. The same event can do both, like a shortage that blocks one delivery and then makes the next ones more expensive.
Example: a sudden increase at a provider
A fictional example. In March 2021, a group entrusted the hosting of its servers to a provider for four years, with an annual adjustment on a labor cost index capped at 3%, nothing on energy and a hardship clause with no threshold (“the parties renegotiate in good faith”). Eighteen months later, the adjusted price reaches $50,000 a month. The provider writes that its electricity bill has tripled, invokes the clause and announces a 25% increase starting the following month, or else it will suspend the service. The threat is the weakest part of the letter: it has to keep performing.
The buyer goes through the conditions:
- According to the provider's figures, electricity accounted for $6,250 a month, or 12.5% of the price. Tripled, it costs $12,500 more: exactly the 25% asked for, so the whole extra cost for the customer. With the 10% margin it reports ($5,000 a month), it is losing $7,500 a month on the contract: the claim of excessive cost has to be taken seriously.
- Whether the change was unforeseeable in March 2021 can be argued, as can the acceptance of the risk: the index does not measure the price of energy, but the price is fixed apart from the adjustment.
Refusing outright would invite a dispute and, for a critical service, risk a migration the customer did not choose. The customer can propose a supplement of at most $6,250 a month (12.5%, half the extra cost) for twelve months, reviewed each quarter on the electricity bills. Over a year, it pays at most $75,000 instead of $150,000. The agreement goes through a contract amendment, which gives the hardship clause a threshold and an exit for the future.
DefinitionContract amendment: definition, when and how to write oneThe amendment to a supplier or services contract: definition, when you need one, how to write it, how to price it and how to refuse one.Read the definitionFrequently asked questions
Does US law recognize hardship without a clause?
Not as a general rule. Courts excuse performance in narrow cases only, and a cost increase alone rarely qualifies. That is why the subject is dealt with in the contract. Ask your counsel what the law of your contract says before answering a supplier that invokes it.
What is the difference between hardship and force majeure?
Force majeure covers performance that an event prevents; the obligation is suspended. Hardship covers performance that remains possible but has become excessively costly; the party keeps performing while the contract is renegotiated.
Can a supplier raise its prices by invoking hardship?
Not on its own. A hardship clause gives it the right to ask for a renegotiation, with figures, while it keeps performing at the contract price. If the discussion fails, the clause sets the exit; it does not let one party impose a new price.
Sources
Published on November 27, 2026
General information, current as of the date shown: it does not replace advice from a legal professional on your situation.