In short
A liquidated damages clause sets in advance the amount a party will owe if it fails to perform or performs late. In a supplier contract, it takes the form of delay damages or service credits. A court enforces it when the amount is a reasonable estimate of the loss, and refuses it when it works as a penalty.
What are liquidated damages?
Liquidated damages are an amount the contract fixes in advance for a given failure. In a supplier contract, that means a set amount per day of delay or per hour of outage. You do not have to prove the amount of your loss, and the supplier has a reason to meet its dates, since each day of delay has a price known beforehand.
The clause is among the essential clauses of a supplier contract and one of the responses to a breach of contract.
Liquidated damages or penalty
The line matters more in the United States and under English law than in civil-law countries. For sales of goods in the United States, damages may be liquidated “only at an amount which is reasonable in the light of the anticipated or actual harm caused by the breach”, and “a term fixing unreasonably large liquidated damages is void as a penalty” (UCC § 2-718). Courts apply comparable tests to service contracts, state by state. Civil-law countries such as France accept penalty clauses, and let the judge reduce an amount that is manifestly excessive.
In practice, in a contract under US or English law, the word “penalty” works against you. Call the amounts liquidated damages, and keep the calculation that led to them.
| Mechanism | Origin | Effect |
|---|---|---|
| Liquidated damages | The contract | Compensate for a supplier failure with an amount agreed in advance |
| Late payment interest | The contract or the law | Charged to the customer that pays late |
| Limitation of liability | The contract | Caps compensation for the proven loss |
A low amount presented as the “sole and exclusive remedy” works as a limitation of liability under a more reassuring name.
SLAs and service credits
The credits of a service level agreement follow the same logic: an amount fixed in advance for each missed level. Three points are up for negotiation:
- automatic application: a credit that has to be claimed in writing within ten days is lost the first time the contract owner goes on vacation;
- the monthly cap, and the right to terminate if failures repeat, for example three months out of twelve;
- the “sole and exclusive remedy” wording that cloud providers usually attach to their service credits: for a critical service, refuse it.
Drafting and calculating the clause
Liquidated damages are calculated this way: a base, multiplied by a rate and by the number of units of failure, within a cap. Write down each term:
- the base: price of the deliverable, monthly fee or fixed amount;
- the unit: calendar or business day, business hour, increment of 0.1 point of availability;
- the starting point: planned delivery date, logging of the incident or notice;
- the cap: per failure, per month or over the term of the contract;
- the payment: deduction from invoices after written notice, or an invoice from the customer.
A fictional example: an application managed services contract invoiced at $40,000 a month, with a migration project whose phase 2 costs $120,000.
| Failure | Calculation | Amount |
|---|---|---|
| Phase 2 delivered 15 business days late | 0.5% × $120,000 × 15 days | $9,000 |
| Availability for the month: 99.5% instead of 99.8% | 3 increments of 0.1 point × 2% × $40,000 | $2,400 |
| Blocking incident fixed in 7 business hours instead of 4 | 3 hours × 2% × $40,000 | $2,400 |
The service credits for the month ($4,800) stay under a monthly cap of 15% of the fee, or $6,000. The damages for phase 2 would reach their cap of 10% of the price, $12,000, on the twentieth business day. Beyond that, the delay costs the supplier nothing more, which is why you need the right to terminate.
For the amount, start from the foreseeable loss: working hours lost, invoices issued late, a workaround. Too low, it does not deter; out of proportion, a court can treat it as a penalty. Keep that calculation on file: it will justify the amount if it is challenged. A buyer-friendly sample clause:
Section [X]. Liquidated damages [X].1. If a Deliverable is delivered after the date set in Schedule [ ], the Provider shall pay the Customer [0.5]% of the price of that Deliverable per business day of delay, up to [10]% of that price. [X].2. Failures to meet the service levels of Schedule [ ] give rise to the service credits set out there, up to [15]% of the monthly fee. [X].3. These amounts are due without prior notice. The Customer may deduct them from what it owes the Provider after informing it in writing. [X].4. The Parties agree that these amounts are a reasonable estimate of the Customer's loss from delay or degraded service, and not a penalty. They are not the Customer's sole remedy: the Customer keeps the right to claim compensation for losses of another kind and to terminate the Agreement. Reaching a cap is a failure within the meaning of Section [ ] (termination). [X].5. These amounts do not count toward the liability cap. Those already accrued remain due after the end of the Agreement.
Amounts due without notice, a non-exclusive remedy and amounts outside the liability cap are customer-friendly positions that have to be negotiated; have the clause reviewed by your counsel. Where the clause requires written notice first, our notice to cure letter gives you the wording. For contracts already signed, Naigo extracts the clauses you describe in plain language, liquidated damages included, each with its source (see supplier contract management).
Free templateNotice to cure letter: template and procedure for a supplier breachFree notice to cure template for a supplier or provider in breach: contents, cure period, delivery, and what happens next. In Word.Download the templateWhen a court looks at the amount
Under the US test quoted above, an amount that is unreasonably large is void: you are then left to prove your actual loss. A civil-law judge would reduce it instead. In both systems, an amount with no relation to the stakes is the one at risk.
A fictional example: 2% of a $500,000 contract per day of delay, with no cap, comes to $300,000 in thirty days for a secondary deliverable. Such an amount invites a challenge.
Liquidated damages and other remedies
When the clause is silent on the point, the agreed amount usually stands as the compensation for the failure it covers: if your loss from the delay is higher, you will not easily obtain the difference. Write what the amounts cover and what stays open: losses of another kind, and the right to terminate.
Delay damages do not release the supplier from delivering. Say so in the clause: the amounts are owed for the delay, and the deliverable is still due.
Frequently asked questions
How do you calculate liquidated damages?
Multiply the base (price of the deliverable, monthly fee) by the rate and by the number of units of failure, within the cap. A fictional example: 0.5% of $120,000 per business day, over 15 business days, comes to $9,000.
How much should liquidated damages be?
No rule sets a rate. Start from the foreseeable loss and choose an amount that deters without being out of proportion, or a court may refuse it as a penalty. Add a cap, and keep the calculation.
What is the difference between liquidated damages and a penalty?
Liquidated damages estimate in advance the loss a failure will cause. A penalty aims to punish, with an amount unrelated to that loss. US and English courts enforce the first and refuse the second; civil-law judges accept penalty clauses but can reduce them.
Sources
Published on November 27, 2026
General information, current as of the date shown: it does not replace advice from a legal professional on your situation.